09-04-2013 2:30 PM
Hi all,
I am trying to create a PO, but shipping tab is not getting enabled for me.
I did below settings, but still it is not coming up.
1) Assigned shipping points
2) Assigned delivery type & checking rules
Thanks!
09-20-2013 6:31 AM
Hi Venkatesan
Please have a look on the below points,
1. Logistic Execution - Shipping - Basic Shipping Function - Shipping Point & Goods Receiving Point Determination - Assign Shipping Point ( USE DC )
2. Material management - Purchasing - PO - Set up Stock Transport Order - Assign Delivery type and checking rule
3. Material management - Purchasing - PO - Set up Stock Transport Order - Assign Document Type ,One step procedure,under delivery tolerance
4. Check the loading group defined in the basic data of the article master record and in Point 1 & check the shipping condition in the customer in the site master record
5. Check the tcode-OVL3
6. Ensure that site(store -customer) is extended to distribution mode(Distribution Channel)
Shipping tab will appear in STO once you have completed the above settings
09-11-2013 9:52 PM
Hi,
In the customizing of the site (WB02--> customizing for plant), on the sales tab, Org. Unit shipping point per plant,
You need to create a shipping determination key:
Shipping condition/ Loading group (of your article) / Plant / Proposed shipping point (your shipping point).
Check the Loading group on your article is the same on the determination.
09-17-2013 10:03 AM
Hi,
The receiving plant customer should be extended to the supplying plant distribution chain. So in change site (WB02), go to customer and extend the customer to the DC distribution chain.
Apart from this, Shipping point assignment should be there and shipping condition should be updated in the extended customer.
With these settings, it should populate the shipping tab.
Regards,
Amit
09-18-2013 12:06 PM
Hi Venkatesan,
Go to SPRO-> Materials management->Purchasing-> Set up Stock transfer order -> Assign delivery type and checking rule -> Enter document type -> Delivery type -> enable check box shipping.
Hope this helps..
Regards,
Vikram
09-20-2013 6:31 AM
Hi Venkatesan
Please have a look on the below points,
1. Logistic Execution - Shipping - Basic Shipping Function - Shipping Point & Goods Receiving Point Determination - Assign Shipping Point ( USE DC )
2. Material management - Purchasing - PO - Set up Stock Transport Order - Assign Delivery type and checking rule
3. Material management - Purchasing - PO - Set up Stock Transport Order - Assign Document Type ,One step procedure,under delivery tolerance
4. Check the loading group defined in the basic data of the article master record and in Point 1 & check the shipping condition in the customer in the site master record
5. Check the tcode-OVL3
6. Ensure that site(store -customer) is extended to distribution mode(Distribution Channel)
Shipping tab will appear in STO once you have completed the above settings