QA07_Recurring Inspection_Next Inspection Date_Based on SLED from Manufacturer

former_member221025
Active Contributor
0 Kudos

Hello guys,

We have some Raw materials for which we need to apply recurring inspection.

1. Inspection interval in QM view: 730 Days.

2. 09 Inspection type active in QM Setup.

3. Next Inspection date for Batch is calculated at the time of Creating batch i.e Goods receipt.

A. Manufacture has Expiry period of 730 days for Same material.

B. Suppose, manufacturing Date is 22.04.2013 so Manufacture's SLED is approx 21.04.2015 (is also recorded in GR Doc.)

C. We have done GR on 09.08.2013, So Next inspection Date for the Batch is 08.08.2015. Which i guess is not accurate at all.(Technically it is right though)

We want Next Inspection Date to get updated as 21.04.2013.

Is there any Solution?

Regards,

Amol Manave

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor
0 Kudos

You will need to identify and use a user exit during your GR process and provide coding to adjust the next inspection date according to your requirement.  There is no simple configuration change that can address this.

FF

former_member221025
Active Contributor
0 Kudos

Thanks for the Reply FF.

i will check for customization in GR process.

Amol