on 09-03-2013 7:49 AM
Hello Team
While doing a foreground run in rrp3 and If i step in such an error like
""
Message no. /SAPAPO/RRP_HEUR093 "
what could that mean ?
unfortunately google has all the answers except an answer for this .
Do i need to readjust the config. settings in product master ?? since any run has a direct bearing on product master . or Do i need to re adjust the date /time/horizon settings ??
even a slightest clue from you could help get down to the root of the issue ...if need be i will send a doc. on all the steps i have taken so far for you to perceive better.-a bit curious to know on what that error means.
in snp tab of MAT1 i fixed 10 days as horizon and in PP/DS tab i fixed 24 days as horizon..does it require any readjustment ?
thanks
Hi
The Heuristic Run is Successful.Warning are Issued Such that there may be any Plan Delay or Shifted.Orders may be Delivery after the Expected Date.Please Click on the Message to Know More Details.
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.