hi all,
we have implemented cproject 4.0.
we are working on R/3 ver 4.7
after allotting the resources to tasks and confirming the tasks, how can i retrieve the resource cost from R/3.
In cproject i dint see any tab for resource cost.
pl help
thanx in advance
Niranjan
Hi Niranjan
Resource cost tab will be visible only after you have:
1. created cost/revenue rates in cProjects: SAP Customizing Implementation Guide -> Collaboration Projects -> Connection to External Systems -> Accounting Integration -> Define Cost/Revenue Rates
2. Assigned the cost/revenue rate created in step 1 to project role types:
SAP Customizing Implementation Guide -> Collaboration Projects -> Resource Management -> Basic Settings for Project Roles -> Define Project Role Types
3. Set up accounting integration in Project Types: SAP Customizing Implementation Guide -> Collaboration Projects -> Structure -> Define Project Types
4. Perform steps of Accounting Integration:SAP Customizing Implementation Guide -> Collaboration Projects -> Connection to External Systems -> Accounting Integration
Do read the documentation with the customizing.
Regards,
Reema.
Award points to all useful answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanx Zhenbo
i have checked in evaluation tab @ actual cost, bt the tabs dint show any values however headers are there..
the headers present in the Evaluation tab are as below,
ProjCstPln
PjCstPlan2
OrdCstPlan
Order CP 2
PrjRevPlan
ProjRvPln2
OrdRevPlan
OrRvPlan 2
Budget
Release
Res. Plan
FxdPr.Comt
CostCommit
Act. Costs
Act. Revs
Disburs.
Payment
but No Valuesss???
Pl help
thanx in advance !!!
regards
Niranjan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Niranjan,
Normally the field ' Act. Costs' should displayed the costs, which be booked due to confirmation. My questions are:
1. Is the CO objects (internal order or WBS) replicated corrected, you can check it in the tab 'accouting' in the cProject.
2. Is there really actual costs booked by confirmation at all. You can check it in the background system, where the confirmation is done. You can check using reporting transaction or run the t-code rkacshow to let the involved controlling object be displayed, check then the item COSSA.
3. If point 1 & 2 are O.K. then there is may be a problem with evaluation. Please then go through then the customizing settings of evaluation.
Kind regards,
Zhenbo
Hi Niranjan,
As far as I understood, you can confirm the tasks (with a controlling object, replicated by the cProject). With the progress you made, the customizing setting for co-integration have been done correctly.
To retrieve the resource costs, I think, you mean the actual cost which caused by the confimration, not the planned costs, the evaluation is the only way I know to get it. Please check it out.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.