I am not able to use mass conversion of planned orders to production orders for more than 100 planned orders at a time.
If the planned orders are more than 100, the conversion indicator doesn't get set to any order. Because of this I have to always make sure that I load only 100 planned orders in one go.
Please help me know the configue setting which restricts the maximum number for order conversion.
Thanks
Hi Suresh,
Have you used the BADi /SAPAPO/RRP_ORD_CONV method RRP_CHECK_ORD_CONV Order Covertibility Check? Here you can define customer specific check it can be work with conversion rule set in product master or Global Parameters and Defaults setting conversion rule is defined in Execute tab. Please check the same.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Suresh,
Please check the below thread:
http://scn.sap.com/thread/710158
There is no restriction in conversion like max limit 100
You can try scheduling a background job for the report RRP7 to convert the planned orders to production orders.
Hope this helps
Regards,
Swetha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.