Hi All, could you please describe how SAP calculates SCRAP figures in CO03. Which menu should I use to gain figure in CO03
Thanks
Regards
Petr
Hi Petr,
I did a quick search on SCN and found the following:
In CO03 the scrap field is the one you plan for, either entered manually or picked from the value maintained against the assembly scrap.
The scrap you are able to see in CO14 is the actual scrap posting done while production.
So even if you do not plan for any scrap but you can post the scrap while confirming the order.