How to go with MTS planning with SNP & MTO with PP/DS

Former Member
0 Kudos

Hi All,

Can anyone suggest how to do MTS Planning with SNP & MTO with PP/DS.?

Regards

Harsh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Hars,

First you can't have two strategies for the same SKU. To be able to deal with MTO at SNP level you have to use CTM SNP and then you can use PPDS at the next level.

Thanks, Marius