SC creates req in back end, should create a PO.

Former Member
0 Kudos

Hi experts,

We are running SRM 5.0, and i have a question regading req. created in back end, even the system is customized for creating a PO in back end.

My question is:

If I have created customizing in 'define objects in backend system (Purch, Reqs, Reservations, Purch, Orders)'. In this customizing I have created a purchasing group 50000019, to create PO if item data is complete, otherwise req.

50000019      *      QSACLNT400      Purchase order if item data complete, otherwise purch. req.

If I create a SC using another purchasing group (50000099), will the back end then create a req., and not a PO?

Best regards Kim

Accepted Solutions (1)

Accepted Solutions (1)

konstantin_anikeev
Active Contributor
0 Kudos

Hi Kim,

you should make customizing for all purchasing groups.

Technically: those data will be tranferred to backend via function module BBP_INTERPRETE_DATA and Backend decides, which document to create. If no entry there, a reservation or purchase requisition to be used.