on 08-22-2013 11:10 AM
Hi,
in my Change Request ZMCR I use the approval Procedure SMCR0001, but instead of the Change Manager Function which is normaly used for approval, I do use an own Z-BPFuction Called Change Coordinator ZDCR0011. Which is also configured in the Approval Procedure. Sadly, when I fill in the BP in the header of the Ticket and choose the approval Function, the BP is not copied into the approval assignment block. When I connfigure the procedure to use the Change Manager it is working.
Does anyone have any Idea, why it is not working with Z-Functions?
Thanks and Best Regards
Alex
Hi,
thanks for your answer, but I do not understand what you mean.
Best Regards
Alex
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Here are some things you might want to check;
1. Define Partner Function
you need to maintain the Change Cordinator as Employee, as you see from my screenshot I have 2 additional Partner functions CGMP Team and Business Manager here
2. Define Partner Det. procedure
Your Partner Function 'Change COrdinator' should be part of Partner Functions in Partner Det Procedure. You can refer to my screenshot
And in User Interface Settings;
3. Partner Function used in CRM UI
I used Partner Number 9 and Partner Number 3 ,Partner Number 4 for my 3 level approval procedure
That's all you need.
Regards,
Vivek
Hi Alex,
You can check the Rule Policies.
Go to the workcenter "Service Operation" and search for Rule Policies.
You should find the rule policy AI_CM_CR_RFC_STE
Check out the rule which is present for SMCR and replicate it for your ZMCR and your approval procedure steps.
This rule is responsible for copying the partners you enter in the header on the Details assignment block to the Approval assignment block.
Kind Regards,
Joyca
Thanks Joyca, I had forgotten to attach screenshot for this part in my reply. That should have helped to solve the error.
Here is how my Rule Policy looks like; please navigate here as adviced by Joyca above.
So basically you create new rules for each of your Z Partner Functions here. As you can see, I have 3 Rules here because my partners are IT manager, Business Manager and CGMP team.
sample rule would be like below one of the Z Partner Function
If
Approval Procedure Equals General Approval Procedure and
Approval Step Equals IT Manager
Then
Set partner for step approval by PFC ( Partnerfunction = ZSIGMA01:IT Manager )
Hope this helps...
Regards,
Vivek
Hi Juan-Carlos,
You were almost there
The bottom icon, with the {-} symbol, contains an actual rule. If you select it, you see the standard SAP Rule, which reads:
|
You can use the function More - Edit Released Rules As Draft to edit and add rules.
If you want to create a new role, set your position on the "folder" icon and press the "create subnode" button. Or you can start with a copy of the existing standard rule.
The rule "code" is easy to adapt with the help of the Conditions and Actions block. Just replace the inputs by your own approval step codes and partnerfunction codes.
When you are done, don't forget to use More - Release Draft Rules and Save!
Many thanks indeed Joyca.
Even though we did have the rules in place, I do not know exactly why it was not working, but now it works, so we are happy.
Many thanks indeeed. I finally made click on this one, thanks to your help.
Alexander: I would recommend you may delete and re-create your rules relate to this. They should work.
Regards,
Juan
Hi Sateesh,
In your first screenshot, you use a rule policy called "BG APPROVAL". If you want to use another approval procedure than the standard one (AI_CM_CF_RFC_STE) then you need to make additional customizings in IMG activities "Define Service Manager Profiles" and "Define Approval Settings" to change the rule policy that will be used.
Your second screenshot does come from the standard AI_CM_CF_RFC_STE). But you defined your three steps in a hierarchy, while they should be on the same level.
Always select the higher level node (the folder icon) when adding a new rule, as it will always be added as a lower-level-node.
Also, please note that the AI_CM_CF_RFC_STE rule policies is for determining the partners on the Steps of your approval procedure, not the approval procedure itself.
For determining the determination procedure itself, you need the rule policy AI_CM_CF_RFC_PRO.
Also, if your new custom approval procedure does not even appear in the manual dropdown list, then you will need to check your approval procedure customization. Is your new approval procedure assigned to the correct approval procedure determination procedure? An is this approval procedure determination procedure assigned to your transaction type?
You can always go have a look to these blog posts:
Kind regards,
Joyca
Hi Joyca,
Thanks for quick reply. I have followed above blogs ZMCR-CUSTOM3 and step 2 RULE and done all the changes required for customized rule policy but I will change the order of nodes as per your recommendation and see whether it makes any difference.
I am bit worried that CRM_UI is not picking up ZMCR0001 instead it is picking up SMCR0001
Will let you know once I have done the changes
Thanks
Sateesh.
Hi Sateesh,
Can you upload some screenshots from your checklist customizing?
IMG activity Define Approval Settings.
Especially "define approval procedures", "define approval determination procedures" and "assign default approval procedure".
Also, what is in the rule policy AI_CM_CF_RFC_PRO?
Kr,
Joyca
Sateesh Volimineni wrote:
Here you fo Joyca
Can you click one step further on the last customizing activity?
Select ZMCR0001 and check in "assign default approval procedure". Your Z approval procedure should be there instead of the S one.
You can also add multiple approval procedures there, to still allow to choose via the dropdown list.
Then for the approval procedure AI_xxx_PRO, that rule should look more like this;
Thanks Joyca it worked:) as soon as I removed S series under assign default approal procedure and changed the AI_XXX_PRO rule as per your screen. I can see three options now
Two more queries
1) so I can add developer,tester and IT operator under customized approval process so that they can approve one by one ?
2) Do we have any option of email setup in between approvers in approve section so that they can approve?
1) Yes, if you want them to approve one by one then make sure that you add the three approval steps in a sequence, but looking at your previous screenshots that seems to be done correctly in the customizing of "define previous steps".
2) For this I can refer you to the help text of the IMG activity: "Make Workflow Settings for Request for Change Approval" to activate the workflow for Approvals.
Then, you can have a look at the thread where it is explained how to get the workflow tasks to be sent as e-mail as well.
Hi Joyca,
Quick one,
I am getting issue while generating normal change document once request for change is approved.
Please find screenshots. This is a demo setup so I have created mutiple client 500,600 and 700 in solution manager only. Maintenance cycle looks good and LMDB component looks fine.
Please assist
Thanks
Sateesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.