Required A Field In Inspection Plan At Plant Level

former_member288833
Participant
0 Kudos

Hi,

We want to requred a field in inspection plan at  plant level.can you guide me. is it possible?

Field Name:- PLMKB-QERGDATH (Origin results data).

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184536
Active Contributor
0 Kudos

Hi Ram

You cannot do at Plant Level. But you can make this field mandatory in inspection plan on the basis of MICs and MICs are created at Plant level. I thingk it will resolve you problem.

regards

Manish

former_member42743
Active Contributor
0 Kudos

Not possible that I am aware of. 

If you use CWBQM transaction for plans you could use the provide Badi for checking plans.

You might also look at EXIT_SAPLCQBM_002 and see if you can write your own check.  I'm not positive on this exit however.  I saw it in another posting and I have never had time to check it out.

If you do, please report your findings back to us.

Thanks!