Hi ,

We are in the process to have a Q/A environment added to the 3 tier Dev->Test->Production, so

Dev->Test->Q/A->Production . We want Q/A to have the same master data as Production and can do

that for the Material and BOM and Prices, etc ... with PDR ( SAP Product Data Replication) .

What about Customer master data and Customer Hierarchy master data ? Do SAP has a technique to

transfer real time via ALE or other technique from one ECC 6.0 system to an other ECC 6.0 system ?

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

Talk to your basis team, who can help with that.