After transferring PPM from SAP, I am getting error that "Operation  0041 contains only one activity" in APO.

In SAP I checked Master receipe, phase relationship and all looks correct to me.

what might be the problem

Ravi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ravi,

  Do you have any setup phase in the recipe ? if so it should have a preceding processing activity. Can you please check if it is case ?