cj31 and s_alr_87013558 report budget values are different

former_member412338
Participant
0 Kudos

Hi All,

I get the different values in CJ31 (say 1000) & in S_ALR_870558 (say 900).

I checked all possible options, but couldnt find the difference amount of 100 .

Even tried to run n fix with CJEN , but didnt succeed.

Please help me out.

Thanking you in advance.

Accepted Solutions (1)

Accepted Solutions (1)

former_member412338
Participant
0 Kudos

Hi ALL,

Thought of sharing a precise answer of this query as i came to know through SAP AG.

I run the correction programm (BPDIST03) and then everything was fine

once again thanks to all.

Former Member
0 Kudos

Hi Vindhesh,

Nice to know that your issue is resolved after running the correction program.

Please mark your question as answered.

Regards

Tushar

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Vindhesh,

Yes, both transaction and report are not necessary the same. You may see SAP note 1414563 which describes in detail why they are different.

Regards, Gordon

former_member209919
Active Contributor
0 Kudos

Hi Vindhesh,

Check in report CJI8, here you should have the same result than CJ31 but split by line item.

Here you can see year budget and Total budget and also you have one column that it is type of budget.

I think this report can help you to identify why you display differents values.

Regards

former_member412338
Participant
0 Kudos

Thanks Clara,

I already checked in CJI8, there also it is showing tatl =1000, but when i calculate line by line it is 900 only.

And surprisingly no difference line of value 100.

I tried to run the CJEN & CJBN, but coudnt fix the problem.

Mr. Chai & Vhora,

I will try to check these notes, n will let u know.

Thanks for ur help.

Former Member
0 Kudos

Hi Vindhesh,

In fact, note 1414563 has no coding correction. It explains why are both report and transaction different. Please compare the selection in CJE0 (ie 12KST1C) and CJ31. You may find some useful outcome. If persist, please update this thread again.

Regards, Gordon

former_member209919
Active Contributor
0 Kudos

Check CJI8 executing with FY = empty and flag Overall Values ( Total Budget)

Check CJI8 executing with FY = 0001 - 9999 and unflag Overall Values ( Yearly Budget)

Are the same amount?

former_member412338
Participant
0 Kudos

Hi Chai,

I compared CJE0 & CJ31 BUT NO DIFFERENCE, BOTH ARE SHOWING 1000, while their manual total is 900.

Hi Clara,

it didnt help, both are showing same plaaned budget value i.e - 1000, but when i calculate it shows 900 and even it is showing 900 in 558 report too.

I guess i need to raise this issue to SAP.

If someone come up with other ideas, most welcome.

former_member203108
Active Contributor
0 Kudos

Why dont you post the screen shots of those reports? It will be helpful for the forum members to analyze your issue better.

former_member209919
Active Contributor
0 Kudos

Hello,

What do you mean " When I calculate it shows 900"? ( where ( appart of S_ALR_87013558) the system shows 900 ?

Former Member
0 Kudos

Hello Vindhesh,

Have u tried to run CJBN. If not, try once running CJBN.

Also refer Note 178837 - Availability control: Incorrect assigned value?

There are lot of threads already discussed in SCN on the same topic. Try searching the same.

Regards

Tushar