Dear all,

While doing stock transfer from  one  plant to another, ideally system should create inspection lot in the receiving plant. After activation 08 inspection type also  system is not  creating inspection lot and material is directly going to  unrestricted stock .

Kindly help in this issue

Thanks in advance

Vivek

Accepted Solutions (1)

Accepted Solutions (1)

former_member208398
Active Contributor
0 Kudos

Dear,

1. Make sure you have 08 inspection type active in the inspection set up data for the receiving plant (QM view is plant specific).

As you are using STO, make inspection type '01' active in the receiving plant.

2. Check in OMJJ setting whether QM has been made inactive for the movement type you are using. Otherwise in SPRO -> Quality management -> Quality Inspection -> Inspection Lot creation -> Inspection for Goods movements

Best Regards,