I am planning to do an enhancement in SNP to offset the component dependent demand when an SNP planned order (for higher level finished good) is created during the heuristics run. Are you guys aware of any SNP BAdI, etc. that will make this possible?
Just to clarify and make it simple, I am looking for a BAdI in APO SNP that will change the dates of the dependent demand during order creation similar to the one available in PP/DS?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sandy,
If you are using PPM , you can enable the option prevent product explosion at the component level to stop the SNP engine to create the dependent demand.By doing this the PPM will be selected for the planning however no dependent demand will be created for the components, I hope this is your requirement.
BR
Thamizh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sandy,
You can check the following thread, which talks about the BAPI : BAPI_PLANNEDORDER_CHANGE
and the function module MD_SET_ACTION_PLAF for Schedule planned order and the transaction MDAC Execute action for planned order
http://scn.sap.com/thread/1661466
Thanks,
Diana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.