on 08-15-2013 7:55 AM
Dear experts,
after activation of an integration model with cfm2 the whole process goes into sleep mode (seen in SM51) and is dot not come back.
That means the process is not ending and the model is not activated.
The deactivation of an existing and active integration model works fine.
Does anyone have an idea what to do?
Thanks in advance!
Heinz
Dear,
Please refer the OSS Note 706312 - Improved performance during initial transfer
If you have huge data in IM please split the IM also you can use activation in background with CFM3 transaction
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Meanwhile we initiated a new client copy, since all actions I took did not solve the issue.
Thanks for the support!
Heinz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Heinz,
Use the program RIMODAC2 and schedule it in the background. Make sure that you're also using the relevant parallel processes to effectively consume the background work processes.
Babu Kilari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.