Hi All,
Can anybody tell how to know the status of the material at each stage in QM ie. starting from creation of inspection lot till the material is released for production. What is the t.code(s) to know the status?
Kindly provide your inputs as early as possible as this is one of the urgent client requirement.
Thanks in advance for all your valuable replies.
Regards
V. Srinivasa Ranganath
Look at the status codes in the QA32 worklist.
CRTD - lot is created but typically has missing data (usually an inspection plan) and can't be processed yet.
REL - lot is available to work on
INSP - lot has had someone accessed it and possibly recorded some results.
UD - Lot has had a Usage decision made.
These are the most common ones. There are others and if you google ones you don't know, you'll quickly find what they mean.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you even TRY to google for these? If you did you would have found this:
http://help.sap.com/saphelp_erp2004/helpdata/en/2d/351956448c11d189420000e829fbbd/content.htm
FF
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.