We have following requirement and process is as follows. Any inputs are highly appreciated.
1) 01 Inspection set up for the material at the material document level and WM is activated but HU is not activated
2) Inound delivery against PO - example 100 pieces
3) Goods receipts in boxes by vendor with vendor bar code tag - 10 pieces * 10 boxes
4) Inventory team scans each box which posts GR (partial receipt) and also prints WM-TO tag. They want WM -TO tag for every ox as soon as it is scanned.
Now issue is as soon as GR (partial receipt) is posted, SAP creates inspection lot and as there are 10 boxes, it creates 10 inspection lot. They really want just one inspection lot for all total 100 quantity. So question is can inspection lot be triggred at inbound delivery level? If not, what are other options?
I know if it is HU managed, we can have inspection lot at HU level with inbound delivery but this is not HU managed.
Thanks in advance for your help.
Regards
Is it batch managed and what is the "control inspection lot" setting in the 01 inspection type setup in the material master?
Please read the F1 help for this field and it explains the choices.
You probably want to try the choice of "Material, Batch, Storage location".
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.