Earliest end date not calculated

Former Member
0 Kudos

Dear Expert,

I have scheduled the scheduling parameter but still the earliest ed date not calculated once scheduled. Is there anything missing?

Please assist?

Regards

Sumitra

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

If you can give more details such as what kind of orders you are talking about & what kind of scheduling parameters maintained (Forward, Backward, etc.,) exactly, then we can think of probable solution.

Former Member
0 Kudos

Hi,

Thanks for your reply. I manage to solve the problem by doing the following :

1. In spro Production>Capacity Requirements Planning>Routing data>Define control key. Ensure the particular control key, the scheduling and det req ticked.

Former Member
0 Kudos

How to close since its solved?

Former Member
0 Kudos

You can mark any reply as correct answer to close or click Assume Answered to close.