on 08-12-2013 8:49 AM
Dear SAP Gugus,
I have one scenario where i have customer where i charge for one day or a week in sap refx, how to map this process in refx, at present it is done from fi
Kindly help, how to raise debit note in refx.
Thanks
Shilpa
Hi Shilpa,
in REFX all GL accounts are linked with Condition Type, so when ever you post (RERAPP) periodic posting for individual contract, condition type will take care of posting in FI.
Hope this will help..
Thanks,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
What is REFX ?
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
REFX is more tightly integrated with Plant maintenance module
as i understood, you have a repair or service performed to the customer in his/her Building or premises
if so, you hve to create a REFX order which is similar to your service order with kind of repair ( operations ) and components for repair
let say, for repair of some leakage, your technician has performed
Inspection -1
Repair -2
Pipe ( material ) - Qty
in the service order you can add everything and based on the hours worked cost will be determined
create a debit memo request with the cost and add some markup
regards,
santosh
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.