Mass change of factory calendar in relationships between avtivities

Former Member
0 Kudos

Hi PS-Experts,

I have hundreds of relationships in which I have to change the factory calendar. Is there a transaction or programm which supports me in doing this?

CNMASS does not offer a possibility to change the factory calendar in relationships.

Regards,

Mike

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member201206
Active Contributor
0 Kudos

Hi  Mike,

the involved field  is 'kalid' in table AFAB'.  It is straightfoward to have create to change the value.

For forget is to run the scheduling afterwards for the changed networks.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Mike,

Talk to your ABAPer and explore if you can use BDC or LSMW.

Regards

Tushar