Hello,

I logged onto one of our GRC non-prod systems (currently on SP10, initial system build in 2011) and all background jobs run before today were missing in the front-end ARA.

Has anyone else ever experienced this or have any insight on why this would have happened?


Thanks,

Marla

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Just want to add one point:

You can exclude the jobs in differentioation specifications of job section if you want some jobs to run without deleting.

Former Member
0 Kudos

Hi Marla,

The job SAP_REORG_JOBS is a
standard job which runs a report RSBTCDEL2 to delete old, canceled,
inconsistent, non-deleted jobs from the system. Your basis team may have
scheduled a job with report RSBTCDEL2 and without any variant. That means background jobs older than 14 days (default) will be deleted from client.  Your basis team can create new variant in
Transaction SE38 specifying the number of day’s range after which the jobs need
to get deleted from the system.

This way your BC jobs will remain in system for longer period.

Former Member
0 Kudos

Hi Marla,

Please work with the basis team to identify if the required background jobs have been scheduled to delete the GRC jobs:

http://help.sap.com/saphelp_45b/helpdata/en/c4/3a7ede505211d189550000e829fbbd/content.htm

GRC doesn't have any mechanism to delete its jobs itself.

Best Regards,