on 08-06-2013 2:12 PM
Hi
I want to Explode a WBS BOM in sales order but when I enter the material and wbs element in sales order Item, the system give the <Message no. V1113 :
The system tried to find a bill of material for the material entered, taking into account material 30000005, plant 1500, date 06.08.2013 and BOM usage ENG1.
However, no bill of material was found.
I set my Item Category as below:
Structure Scope = B (Explode multi level bill of material)
Application = ENG1
and WBS BOM for material 30000005 is created
please tell me how can I Explode a WBS BOM in my sales order.
Thanks alot
Message was edited by Moderator. Remarks: Please don't post your discussion in all Bold or CAPs
Hi,
Please make sure the BOM which you have created has been "Released" (Can see in the BOM - Item Level - CS02) status.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raj;
Thanks for your answer.
My WBS BOM is created by CS74 transaction, and as you say I checked my BOM item level, but there isn't any field named status at item level .
BOM status at header level has been set to Release.
I think it's impossible to explode a WBS BOM in sales order, what's your opinion ?
Regards;
Hi Siavesh,
As rightly mentioned by others,
1. The WBS BOM or network BOM are only used in PS and they are used to trigger material components for the project. These BOM will be exploded when the WBS element is released in the project during which the procurement process may be initiated.
2. Order BOM is purely sales order related and known to all.
The application is different for these and accordingly they get triggered in different modules.