on 08-05-2013 1:22 PM
Hello Gurus,
Wanted to know if once we create Mitigation Controls in the GRC 10 DEV system, can we transport them into GRC 10 QAS and subsequently to GRC PRD system?
Or are mitigation controls not transportable? Early reaply would be highly appreciated as we are about to create the same soon.
Thks.
Ronnie.
Hi Ronnie
I guess it's not possible as mitigation controls are considered as master data.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Mitigation Control is a master data and not transportable. you can create in PRD in NWBC
Thanks,
Arif
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.