on 08-05-2013 3:51 AM
Hello Experts,
I am facing an issue with work time collection plug-in.
Standard value key and parameters as ERP standard are maintained and assigned to a routing / operation step. For this to appear in the POD during "Complete" step, activity LT280 (plug-in for work time collection for labor off) is to be assigned to button "Complete" in the POD. But the activity LT280 is not seen in the activity list.
Also the "How to guide for user maintenance" mentions that it is LT230 is no longer used.
In this case what is the alternative to this activity or how to get the standard value listed in the POD during SFC confirmation?
Thanks in advance
Srinivas
Hi,
Activity for collecting actual time spent should be fired off automatically at Labor Off. See the blog post:
regards,
Konstantin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Konstantin,
Thanks for sharing the link. I have had the chance to see this document some time back and am working along this line only.
Issue I am facing is - In ME 6.1 help document there is mention of activity LT230 which is for work time collection and to be assigned to POD button Complete.
But in ME 6.0 I do not find this activity. How to handle this situation? Would the parameters get listed after all the settings for labor tracking and work time collection are done?
Thanks
Srinivas