Hi Gurus,
When will the material document created in ECC can be seen in under display work list of GTS side Before the posing date or After the posing date.
Thanks & Regards
Karthik.
Hi Karthik,
As Dhilipan says, the transfer of Material Documents is immediate, using RFC.
Regards,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Karthik,
I believed its transferred to GTS as soon as the material doc. is created(creation date)- Synchronous transfer.
I don't think there could be some scheduled prog. to transfer it based on posting date because there could be cases where posting date is diff. from creation date. But let's hear from others as well.
Regards
Dhilipan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.