on 07-31-2013 12:24 PM
Dear experts,
has anybody worked with OTR on confirmed quantities for purchase orders to vendors? How are AB lines (with the vendor confirmed quantities) transferred to TM?
We are facing an issue at our current customer where purchase orders are created and an AB line is later entered manually but the status that is received in TM is complete and therefore not relevant for planning.
On top, if any deviation regarding dates/quantities with respect to the original requested values is introduced, no update is made in TM.
When displaying the OTR in TM we also see how the schedule lines have no value in the confirmed qty field.
Thanks for your advice
Hello Salvador, now the function of acknowledgment transfer is realized.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Salvador,
There´s a set in OTR customizing where you define if the document will be based on confirmed or requested quantities. I dont know if this could help you.
Or maybe you can use BADI /SCMTMS/TRQ_SE_REQREQ in TM to change the info before planning...
Best Regards, Marcelo Lauria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Marcelo,
Thanks for your reply. Unfortunately we already were aware of the OTR customizing activity to select "planning on confirmed quantities". This is exactly what we were testing.
SAP gave us feedback on this point:
- Currently confirmations are not supported in the TM integration. Such a feature is in development and will probably be provided with the newest release
This means that for purchase orders for external vendors we have to necessarily work with OTR type on requested quantities.
Regards
Salvador
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.