on 07-31-2013 10:26 AM
Hi experts
We have scheduled downtime on a resource at mutliple points throughout the day for short interval control meetings; every three hours.
We schedule this down time into the planning board by right clicking on the resource and add these 15 minute meetings in every 3 hours, using Define Downtimes.
Our requirement is to be able to sequence orders through these downtime periods.
Currently when use the hierstic to sequence the orders and they are placed around these downtimes.
We can manually infinite schedule/sequence the orders through the downtime and the time of the order is extended by the length of the downtime. This is what we want APO to do when we use the sequencing function.
Are there any settings in any huerstic that will sequence order through downtimes or do we have to manually do this?
Thanks in advance.
Chris
Hii Chris,
Implement the BADI
" /SAPAPO/CRESDOWNTIME " in APO.
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.