The business scenario has been mapped as below:

5 cost center where production is happening.

       1. 4 cost center are for 4 different major line of product being produced.

       2. 1 Cost Center is for repacking the products produces in the above cost center.

Cost is being brought in via 6 activity types. Activity type are common for all 6 cost center.

1. KP26 - Plan Activity Type maintained manually.

2. CK11N & CK24 or CK40N - Standard Price Calculation.

Now my issue is how is actual activity price computed ?

1.  The Actual Activity price can be computed via KSII. What is the configuration for doing the same.

(Based on the configuration I have seen in OKES, only one activity type can be given. Is there a way to give multiple Activity Type.)

2. Is there a way we can make the plan activity cost in KP26 to be taken for actual computation too?

Regards

Lavanya

Accepted Solutions (0)