Dear Gurus,
I am comparing Actual cost in CJI3 & CN41. Cost in CJI3 is higher than CN41. When analyzed per cost element, we found that the difference in amount is exactly equal to the value appearing against Cost Element- Production Order Settlement Variance in CJI3. Would like to know ;
-what could be the reason that this cost is not appearing in CN41-Actual cost where as its appearing in CJI3-Actual cost?
-What should be remedy the for this?
Appreciate your help in advance.
reg
Rahul Shende
Dear Rahul,
can you check and say which layout you are using for cji3 report. and also plz check the actual cost in cn41 and s_alr_87013557.
Regards
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahul,
CJI3 & CN41N reports even though both of these reports are reflecting actual cost ,the mismacth is happening because CN41N report does populte the report with only actual cost incurred (postive posting) against that project object, where as CJI3 will reflect acutal cost (postive posting) & also settled cost (ususaly it would be same value as actual cost but it would be in negative)incurred against that object hence the resultant would be different in cji3.
Kindly execute CJI3 for that mismatching object & exclude the settled cost posting (Business transaction - KOAO) from the report & compare the resultant with CN41N report.
Regards,
Vadiraj K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahul,
CN41 is tranasction to view the project info system - It gives the stuctural information of project hierachially. Hence it doesn't consider the settled actual cost in it. Where as CJI3 & S_ALR_87013543 are the standard SAP REPORTS. These transaction provides the posting/ planning details considering cost elements.
In CJI3 report even after exluding KOAO business transaction postings if you still noticing the mismatch means there might be chance of other postings apart from settlement which you may be missing.
To summerise this i can say CN41 will provide the output based on project structure. Where as CJI3 is standard SAP report for displaying actuals cost incurred against the project line item wise.Hoping this information helps you.
Regards,
Vadiraj K
Hi Vadiraj,
Ya got your point. But on other side I know the Cost Element from which the diff value (between CJI3 & CN41) is coming from...this cost element is related to the production order settlement variance which is appearing in Actual cost in CJi3. The variance has got settled agaisnt WBS. So basically I can also say that I am not able to see the production order settlement variance which has got settled against WBS in CN41. Hope I am clear.
Reg
Rahul
Both are two different standard reports having different purposes, meaning, CJI3, will give actual cost line items with posting dates (period wise) and CN41 is structure report without actual line items
example;
CN41> Project Definition>WBS element>Network>Ext. processing>Components cumulative at header level (actual costs)
CJI3>Project Difinition>WBS element>Network>Components actual line itemwise positions
Hope this gives some idea about why you are getting mis match figures. But at the end, both the figures definitely match
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Srihari,
As said by you the Actual cost figures should ultimatetly match in both reports. Where as I am receving the difference which exactly equal to the value appearing against Cost Element- Production Order Settlement Variance in CJI3. Would you be able to let me know over this?
reg
Rahul
Hi,
I guess you misunderstood what Srihari has mentioned in his post.
Both CN41 and CJI3 serve different purposes as explained by Srihari. Don't compare these reports. The best thing you could do at this point is check the actual values in the table RPSCO with reference to the object number. Filter the output for value type 4. There are other ways to compare too.
Run GR55, select report group as 6P01 and then input your project and run the report. Compare the values here with the standard report S_ALR_87013531/CJI3 and evaluate.
Let us know what you find.
Regards,
Gokul
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.