on 07-25-2013 1:04 PM
- Dear all,
I can see SNP Planned Orders in the detailed scheduling planning board SAPAPO/CDPS0 twice.
In the section "ressource view" and in the section "product view".
Via mouseover I can see the ID of the planned order in the section product view but the ressorce view I am not able to identify the ID of the planned order.
Is there maybe a possibility to manupulate this behaviour with any provile settings or something like that?
Thank you very much and kindest regards,
Eva
I
Hi Eva,
You can configure this using planning board profile in t.code \N\SAPAPO\CDPSC2. Check what is the graphical object assigned for SNP Planned orders in the resources chart. and see if the graphical objects has the required fields like order number or product number .
Since you are able to see the it correctly in product view, i would suggest you to check how the graphical objects are set for the product chart using the same t.code.
Let me know if this helps.
Rgds,
Kiru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiru.
You write: "Check what is the graphical object assigned for SNP Planned orders in the resources chart." Where is it check? in a transaction? I change the settings OPR_DEF_1, but the changes are not displayed in the section Resource chart. Settings for ORD_DEF_2 in the section Product chart change correctly.
Best regards, Dmitry
Hi Eva,
please have a look at our configuration guide
SAP SCM Detailed Scheduling (S78)
it is contained in
SAP Advanced Production Scheduling rapid-deployment solution
there is an example how to enhance the planning board objects.
BR Frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.