Hi,
I am trying to change planning mode in strategy tab of standard lots PP heuristics (SAP_PP_002). It is greyed out for Forward & Forward+reverse. We would like to use Forward scheduling. Have any of you come across this issue?
thanks in advance,
subramanya
Hi Subramanya,
Make a copy of the heuristic and you'll be able to change it to your requirements.
SAP standard supplied objects should never be changed.
Best Regards,
Mike