Error with CPTK transaction

Former Member
0 Kudos

Hi,

We are upgrading from 6.0 EHP4 to EHP6

When we execute CPTK transaction with the project number P/D83/22/000298, the transaction produce the following error: WBS element does not exit for all the WBS element belonging to the project.

In the image above you can see the error, the WBS element correct number is displayed with green traffic light and the internal number corresponding to the same wbs element is displayed in red traffic light.

We have checked that all the WBS element exist for this project. Can anybody help us?.

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello Alberto,

Did you find the solution for this ?

I am getting the similar error, please share the solution

Thanks and regards

V.S.Natarajan

Former Member
0 Kudos

Please post the error details to help you further with this issue.

0 Kudos

Hi,

You can run the following reports to check for inconsistencie in the project:

- Note 453280 & report ZZADJUSTPOSID

- Note 149698 & report CNHIERAR

It would be useful also to post the 5 digit error code that you are receiving, as this is not evident from the screenshot.

Regards,

Fearghal

Former Member
0 Kudos

Thanks for your answer!

I tryed to lunch the both reports but the transaction produce the same error.

The error code is CJ0021 in the registers with de red traffic light.

Former Member
0 Kudos

Hi,

Check this note,

Note 1853307 - Error CJ021: WBS element PR####### does not exist

Is your project released?

Regards,

Gokul