on 07-18-2013 9:08 PM
Hi guys.
I've been reading that the option of installing in the same sid all the components of SAP Process Orchestration (PI,BPM.BRM) is only possible in java only installation.
Is this afirmation still valid or nowadays exists the possibility of deploying BPM, BRM and PI dual-stack in the same SID?
Thanks a lot.
Regards.
Hi Christian.
It's not possible. You are right saying to use the same SID you should have PO (BRM+BPM+PI) java only. If you want the dual PI stack, you will need to have BRM/BPM in one SID and the PI dual stack in another SID.
I hope it's clear. Please let me know.
Best Regards,
Diego