SD- PS Integration query

Former Member
0 Kudos

Hi,

I am first time working for SD and PS integrated process kindly help me with my requirement

1. when client is excepting project there are multiple activities for what charges are different

e.g   XYZ is a project

and there are different activities like X, Y and Z

so client issue invoice some time separately or some times together for each activity. X is deliverable, Y and Z are non deliverable.

we can not name X,Y and Z as milestone as these are different activities which are going parallel.

can we create different line item in sales order for X,Y and Z?

can we assign different WBS element for each activity but in PS it should be considered as one project.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

As per your busness requirement ,its possible to map the SD process flow with the PS structuring.

Project->Main WBS -> Child WBS Elements->Netwroks->Netwrok Activities.

Asssign only the deliverable item in the SD for invoicing as Deliverable WBS with Operative Indicator Billing Element , And the remaining child WBS Elements as Planning elements. So if the milestones were used for Billing activity , it can be assigned for deliverable WBS elements.

And we can assign different WBS elements in SD line items in SO .

I hope it might be helpful.

Regards,

vrkumar

Answers (1)

Answers (1)

Former Member
0 Kudos

Thank you vrkumar,

can  you please elaborate more, which material type we use for such items

How the wbs element should be delivered wheather by VL01n or CNS0

AT my client place we are not using Milestone billing as there is prepayment process which is a country specific requirement.

Please explain how the process will look like with my requirement?

Message was edited by: Mohamed Rafi - There are many threads which deals about SD PS integration, spend time in searching and referring those.