on 07-16-2013 7:01 PM
Friends,
I was exploring options on one of the Buz scenario to re-determine the scheduling dates in DELIVERY Document, if I change the route in teh delivery.
So if we change the route in delivery, can we have scheduling dates in DELIVERY Document to redetermine, based on the new route.
Greatly appreciate your advise.
Vijay.
In transaction OVLK, you can set if "Rescheduling" is executed in the delivery.
So for example, if you change the route in VL02N and want a new scheduling, you can set "Rescheduling" (in OVLK) to "Y" or "A". This will ensure a new scheduling gets triggered when you change the route
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Route while it does impact the dates in the delivery, it has to do with the Transportation Times. You might want to invoke Availability Check during the Delivery to play with the Delivery Schedules.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.