on 07-15-2013 11:02 AM
Hi All,
When I try to do Plan settlements (CJ9E) I get the following message:
Plan settlement only poss. to receiver categories CTR, BPR, PSG, ORD, WBS
Message no. KD083.
It seems like PS does not allow settlement to an FXA (AUC) for PLAN.
How do I fix this?
Thanks.
Regards,
Hi,
Check this note,
Note 1263198 - ISM-PLM: Planned settlement for non-plan-integr WBS elements
Hope it helps.
Thanks,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Clara,
The reason being currently we do not settle our CAPITAL PROJECTS to the AUC’s created in actual, which cause our process for PLAN and ACTUAL transfer recoveries in SAP PS (IT) to be different. This again caused variances on the reporting when actual and Plan amounts are matched.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Una,
As far as I know Planned costs are only for controlling objects( wbs, cost center , PA...) and you cannot entered them in a FI objec. Then you cannot settle plan costs to AuC.
Why do you need to settle them to the AUc? For reporting you have PS reporting.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.