on 07-14-2013 6:27 PM
Hi folks
We are facing an issue with planned orders which are created in APO when it reaches R3. Some planned orders are showing exception message 52- No BOM selected in MD04.There are two production versions available for this product. Some times exception message occurs in planned orders created from one production version but some times it happens for the other production version.
Production version,BOM and recipe is valid for this product location.
What could be the reason for this?
Regards
Jith James
Hi Jith,
Maintain the selection method as 3 -Selection only by production version in the MRP4 view of the material master in ECC side.
Hope this solve this problem.
BR
Thamizh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.