BO link between cr and cd

Former Member
0 Kudos

Hello experts,

Is there a way by which we can change the project (maintenance cycle) on a correction document without withdrawing it?

I am looking for a table where we can go and change the BO link between change request and correction document

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188058
Active Participant
0 Kudos

Hi Sneha,

Which version are you using? From Solman 7.1 SP05 onwards, this is a standard functionality "Project reassignment" for a CD in Created/In development status. However, the prerequisite for this is that the target project should be in a phase to accpet this change and also the CD should not have any open TR (All TR should be released & Tr.of copies (if any) should be imported)

Hope this helps.

Regards,

Imran

Former Member
0 Kudos

Thanks for the reply, i was looking for it in sm7.0 ehp1