on 07-11-2013 7:23 PM
Hello experts,
I have been given the task of determining what happens when a plant material status of 40 and below is consumed. All I have been able to figure out is that if we consume a part that has a status 20 or a status 20 included in the BOM it will generate COGI errors (Consumption of goods inventory). Is the requirement consumed? SAP does not prevent the consumption of the status 20 part. The group would like to understand all the effects of consuming a status 20 Part. Status 20 for is is experimental build not yet promoted to production.
When a status 20 part is consumed....this happens.
Thanks, Andy
Sorry, Andy, wrong discussion space - this one is dedicated to SAP Manufacturing Execution solution. Please choose a proper ERP-related site here and re-post the question.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.