Project Tasks status update Phase status

Former Member
0 Kudos

We have a requirement wherein when all tasks of a phase are marked complete, the phase is to complete too (automatically).

Does this work? How?    

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Deepak,

No, but there is similar functionality, which complete the task as all subtasks are completed. The note

1740969 contains the changes made to enable that functionality. I may take it as template to do it for the phase.

Kind regards,

Zhenbo