Hello Friends,

We got a requirement on scheduling agreements,for which we proposed LZ document type with forecast & JIT delivery schedule lines.While doing testing we found that though the entire quantity in the scheduling agreement has been delivered,however the respective scheduling agreement is showing status Partially delivered both at header level & item level.

Please advice that whether there is any note to be applied to get the status updated properly.

It would be greatly helpful if you could provide any inputs on this.

Thanks in advance!

Regards

Amar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear A NV,

    Pls chck on the above said settings and also check document flow in copy controls.

Regards

RAM

former_member204407
Active Contributor
0 Kudos

Hi,

what is the completion rule maintained in for your item category LZN?

Try to put completion rule "B" in your item category in vov7.

save it check.

Regards,

Krishna,

Former Member
0 Kudos

Dear Krishna,

We have checked those settings and we tried with completion rule & copy controls settings   but still the status is not completed.Also we noticed for other documents like OR & LP are having completion rule maintained blank in item category TAN & LPN which are in completed status after full  quanity is delivered.We have maintained same settings as well for the docuement LZ but it is never completed even full quantity delivered.

Can you please give me some clue on this whether any note we have to implement.

Thanks.

Amar

Former Member
0 Kudos

Hi Amar,

Check completion rule assigned to your item category (LZN). Standard setting is blank and therefore it is not relevant for completion. You may change the same if required.