on 07-09-2013 7:22 AM
Gurus,
Am facing a real strange problem. Whenever I create planned orders manually in APO or CIF planned orders from R/3, there is no operations generated in the planned orders.
I checked every possible settings (product master, resource master, calendars, recipe, spro and what not). Nothing was wrong. For a change I tried with PPM, I found the operations are correctly populated in the planned orders!
Anybody has a clue on this? Anybody faced such problem?
Would like to add one thing.. system is able to read the supply source in the planned orders, but not able to read the operations in PDS.
Anybody has any clue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have checked the DS board.. what surprising is operations are visible in the resources (resources are visible in the rrp3 screen as well!). I can even drag and drop operations. But when I double click on the operation system says:
Message no. /SAPAPO/CDPSFUNCDISP030
Let me know if anyone of you have faced any similar problem.
Thanks
Hi,
You meant there are no operations in the PDS transferred? If there is no operations in the PDS, there will not be any operations in the Planed order. So, first you have to fix your PDS.
Try to retransfer the PDS using RIMODINI report. This should transfer the operations to APO PDS.
Then try to create a planned order.
Also, please check in the product master PPDS tab, the Plan Explosion is set as '5'.
Regards,
Manimaran M.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.