hi

may i know what is the tcode to

  1. fetch list of snp orders available in the system
  2. convert snp planed orders to ppds planned orders
  3. fiming of snp planned orders

Accepted Solutions (0)

Answers (3)

Answers (3)

sourabh_jain66
Active Contributor
0 Kudos

Hi Rahul,

Use tcode /n/sapapo/rrp4 to check required SNP orders.

Tcode /N/SAPAPO/RRP_SNP2PPDS for converting SNP order to PPDS orders.

Firming of SNP planned order, unfortunately we don't have any Tcode for this, if you want to firm SNP planned order then there are few ways;

- Manually change the orders, it will make them firmed.

- Convert orders to PPDS for making them kind of fixed for SNP.

- You can also use PPDS planning fence for fixing the plan

Another way you can create your own heuristics to suite your requirement using the BADI  - /SAPAPO/CDPS_FDISHEU . For more details pls refer to Note : 453864

Rgds

Sourabh

former_member205751
Participant
0 Kudos

thanks saurabh will introspect on your input

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can do all this with /SAPAPO/RRP4, /SAPAPO/RRP1 - Requirements View for all products and single product through /SAPAPO/RRP3.

Any manual changes to an order it will get firm or you can convert them in PPDS order too. Or you can define the PPDS horizon so order under PPDS will become firm for planning run.

Also you can use /SAPAPO/RRP_SNP2PPDS - Conversion of Supply Network Planning -> Production Planning.

Regards,

R.Brahmankar

former_member205751
Participant
0 Kudos

thanks rupesh....will introspect on your idea

Former Member
0 Kudos

Hi Rahul,

You can use t.code /sapapo/rrp4 for getting the list of SNP orders and convert them into PPDS orders and also you can use the same for firming.

Rgds,

Kiru

former_member205751
Participant
0 Kudos

thanks kiru.....let me try