Dear Experts,
Please give some light of automatically creation of Project in PS from item in PPM.
I have done all required configuration in PPM but it is not getting replicated in SAP PS.
and how questionnaires can be linked to item.
Rgards
Rama Shanker Sahrma
Hi,
Related to your second question "assign questionnaire to item field"
1) SPRO, PPM, portfolio management, global customizing, define custom field configuration, Object type RIH, field config
Here you need to assign the field to the service "questionnaire" 0000000000006
2)you have to " configue" a specific questionnaire assigned to your item in the bucket.
Go to the item superior bucket , miscellaneous tab, field service configuration and here you can assign the questionnaire to one item field
When you create an item, field questionnaire won't be available, only after saving it you can complete it.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
7 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.