on 07-06-2013 8:39 AM
Dear Experts,
I have allocated cost value from cost center to WBS element using distribution cycle (KSV5). ( On Development Sever)
But WBS is not checking the available budget, it doesn't give any error message although already exceed the budget.
Before, you could reply. Please go through the settings/customization that I have made.
Actually,
I have only two WBS with level 1 and 2 respectively I have allocated a budget of 2000 Rs INR on level 1 WBS and 1000 Rs INR on level 2.
Please go through the screen shot of CJ31.
After that I have a cost value of Rs 12000 on my cost center and I have distributed that cost to my Level 2 WBS on which only RS 1000 INR was assigned.
The cost is reflecting in Budget Reports and FI Reports. Please go through Screen shot of S_ALR_87013542 and S_ALR_87013558 Reports.
S_ALR_87013542 Report:-
S_ALR_87013558 Report:-
Furthermore, my tolerance limit is ok. It has been set as ++ For Tr. Grp and Usage as 90%, 105% and 110% with Act. 1,2,3.
My question is why the system didn't stopped me or threw an error when I was running KSV5. ????
Regards,
Amit
Hi Amit,
This is standard system behaviour. Please see to SAP note 865855 for the reason why you did not get any error message.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gordon,
I have gone through the note referred by you. According to note number 865855, System was supposed to generate warning instead of an error message but in my case even warning didn't came. It bypassed the entries and saved it without any kind of stoppage whatsoever.
Moreover, system is taking entry If I do actual cost transfer to WBS ie. using KAFD transaction also. So in both cases, KSV5 and KAFD, system is accepting cost on budgeted WBS despite the budget cost in that WBS is very less than the actual distribution.
Regards,
Amit
Hi Gordon,
Thanks for your valuable reply, but again things are not working. After running CJBW and CJBN in sequence also, system is accepting the higher cost despite WBS being lower cost budgeted. It seems like it is a standard functionality but even though I am looking for the integration/customization with FM(Funds Management) and CO (Controlling) with PS.
I Hope to get any clue from there..!
Thanks,
Amit
Its Std SAP design, refer this note
Note 160971 - Allocatis: warning instead of error msg of availab.control
and I checked it in my system too, it issues warning message instead of error, during KSV5.
Hello Amit,
Could you check for your budget profile the "exempt " cost elements? Is your cost element included here?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.