on 07-04-2013 11:22 AM
Dear Experts,
I have a doubt in Milestone trend Analysis. I am aware that Milestone trend Analysis is used to track the progress of the activities for the given dates in a project. I have attached each milestone to each Activity. And I triggered Usage Milestone functions, Progress Analysis and Trend analysis check box. I have not given any % or dates in Basic data of Milestone.
I released the activity and confirmed the work and days of the Activity. In one scenario I had confirmed (final confirmation) according to the schedule andsaved. I checked CNMT or Clicking Milestone trend analysis icon in Planning Broad, only the Milestone points are displayed.
In another scenario, I had confirmed the activity lately of the given schedule, even then I see the CNMT same..There is no any delay graph or any other kind of graph..
May I know whether I am going in a correct path or missing anything.
Kindly show some light for the issue..
Thanks & Regards,
Seshagiri
Hello Seshagiri,
Please refer following SAP note
Note 380572 - Milestone Trend Analysis in project planning board
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.