Hi Friends,

Let me know how to RFQ phase should not be changed back to “Open for Response”, once it is moved to “Close for Response”. i went through some forums and understand that it is feasible at script level. Do we have another option to restrict the phase change to previous phase.

Thanks

Vimal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Vimal ,

There is no standard way to restrict , you got to do it by scripting . That is generally allowed as some times it might happen that suppliers forget to submit their response and the RFX might get closed for response.

Thanks