I create Configurable material A and material variant B , and in MRP3 view configurable material field for material B I assign configurable material A
After I save I can't change it any more
How to delete Material variant assignment to configurable material ?
Regards
Rami
The correct and standard way would be archive material B and create it again to assign another configurable material.
In SAP standard, it is not allowed to change the assigned configurable material for a material variant after it is created.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rami
Please refer to
http://scn.sap.com/thread/654445
http://www.sapfans.com/forums/viewtopic.php?t=18582
Kind Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You could try this.
Step # 1:
-----------
Go to Material A and change remove the Configurable Check Box, provided the Material Type is FERT. I am not too sure of this if will work if you have already created some orders with this material.
Step # 2:
------------
Go to Material B and see if you get this as an editable option. If yes, remove it
Step # 3:
------------
Go back and put the Material A to Configurable again.
If Step # 1 does not work we don't have any option but just create another Material Set for A & B and live with the old ones.
Happy Testing.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.