on 07-03-2013 7:41 AM
Dear Experts,
My client country weekend has been changed now? In this case from PS side we have to change in factory calenders using in Project Definition, WBS , Network activity, Work center.
Is there any other setting that we can check or any area that will be affected from PS side if weekend has been changed in SAP.
Please suggest. I appreciate your quick reply.
Regards
Hi,
The important thing that you can consider now is the factory calendar. Other than that, as far as i know, there should not be any significant impact on the PS area.
You will get more clarity on this once you run all your test cases as per your business scenario.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sonal,
Since you are not using scheduling/capacity planning, i feel there should not be any significant impact from the PS perspective.
Like i said in my earlier post, running test cases would give a confirmed idea about what areas might get affected. As of now i feel there wont be too much to worry about.
Lets wait and see what other forum members have to say.
Regards,
Gokul
HI Sonal,
There will not be any impact in the system from PS point of view , if there was no usage of Date planning , Scheduling , or Capacity Planning , Prodcution planning ( MRP ) . Since the dates will be captured automatically from factory calender as per the holiday calender definition. Working days will be altered in dellivery date planning & availability Check from SD point of view.
Regards,
vrkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.